Pressure Piping Construction Requirements

QMS written description verification CHECKLIST AB-518b

AB-518b 2014-01

Electronic completion of this document is preferred



Company Name:      




Company Address:      
Title of the written description of the management system or manual(s):

     





Person responsible for the overall management of the pressure piping construction program:
Name:       Title:      


(Capital letters)

Telephone No.: (   )       Fax No.: (   )      




Cell No.: (   )       E-Mail:      





S


(Electronic signature acceptable)
ignature: Date:      

The “Pressure Piping Construction Requirements” document, AB-518 has been issued by the Alberta pressure equipment safety Administrator to specify requirements for the construction of pressure piping systems. In accordance with the requirements of PESR Section 11(1), anyone who wants to construct pressure piping systems in Alberta is required to obtain a Certificate of Authorization Permit from ABSA.


This checklist AB-518b has been developed to assist the applicants and ABSA auditors review the written description of the QMS and verify if it meets the requirements of the AB-518 document and the legislation.
Organizations who wish to make an application for obtaining a Certificate of Authorization Permit in accordance with the requirements of the Pressure equipment Safety Regulation Section 11, shall submit the following documents to ABSA:

  • an Application Form AB-29,

  • an AB-29b Form if applying for multiple shop locations to be certified under the same AQP number (all shops must operate under the same name),

  • a copy of the duly endorsed AB-518(b) document showing where each requirement of the AB-518 document has been addressed in the company’s QMS, and,

  • a draft copy of the written description of the QMS describing the pressure piping construction activity.

Owner/Users who are also authorized to construct pressure piping are required to review their pressure equipment integrity management system documentation and ensure that pressure piping construction activity meets the requirements of AB-518. Owner/Users are not required to submit AB-518b.


ABSA reviewer’s comments:

     


A
(Capital Letters)
BSA Auditor’s Name:       Signature: Date:      

Site Audit records (For ABSA Auditor’s use only)
Project Name:      




Project/W.O./P.O Number:      




Piping owner:      




Audit Notes:

     





AB-518

Sec. #

AB-518 Requirements



*Legend: CAR=Corrective Action Report; Def.=Deficiency

Indicate ‘Section & Paragraph #’ where the requirement is addressed in written description of your QMS?

ABSA Auditor’s use only

Site Audit Results

Remarks/Objective Evidence



CAR*

Def.*

3.3

Quality Manual Requirements




Title Page






Is there a Title Page?
Section 3.3 does not include requirements for the ‘Title Page’ of the written description of a QMS or a manual because it is not a document organizing guide. AB-518 stipulates requirements that must be addressed in a QMS. Inclusion of a Title Page to any credible document is common knowledge, however guidelines for developing a written description of a QMS including a ‘Title Page’ are described in ISIO10013:2001 standard.





Reviewer’s Comments:





Table of Contents

Is there a Table of Contents that lists the number and title of each section and its location in the written description of the QMS?
Section 3.3 does not include requirements for the ‘Table of Contents’ of the written description of a QMS or a manual because it is not a document organizing guide. AB-518 stipulates requirements that must be addressed in a QMS. Inclusion of a Title Page to any credible document is common knowledge, however guidelines for developing a written description of a QMS including a ‘Title Page’ are described in ISIO10013:2001 standard.





Reviewer’s Comments:


3.3.1

Scope

Does this section:

  • describe the scope of the activities to be undertaken?




     


Is the scope of work undertaken within the scope of work applied for?

Yes  ; No 





  

If a company has no shop and undertakes field activities only, the following requirement does not apply. The company shall indicate that the activities undertaken are at field sites in Alberta controlled from an office address of the company.


  • list the shop locations covered under the same registered name, describe scope of work undertaken at each shop location, address of each shop, indicate whether field activities are also undertaken and controlled from this location, title of a person designated to perform QC function at each site, and, the title of a person who is overall responsible for maintenance and assuring effective implementation of the QMS at all locations?



     


Is all information as required by this section provided?


Yes  ; No 



  




Reviewer’s Comments:

     


3.3.2

Definitions of Terms and Acronyms

Are terms and acronyms used within the Pressure Piping Construction written quality management system defined?


     


N/A



  




Reviewer’s Comments:

     



3.3.3

Organization

Does this section:

  • include a statement that the management will ensure that responsibilities and authorities are defined and are communicated within the organization?

     


How are the responsibilities and authorities communicated to the employees?

     





  

  • describes the organization that shows the organizational structure and identify key positions of personnel who manage and perform work affecting quality?

     

Does the organization structure as defined in the QMS manual match with the organization structure in practice?

Yes  ; No 



  • Is the organization structure suitable for the organization?
    Yes  ; No 



  




Reviewer’s Comments:

     


3.3.4

Statement of Authority and Responsibility

Are the following statements made?

  • a statement that the documented QMS meets the requirements of the AB-518 document and accurately describes the pressure piping construction processes implemented by the company?




     


N/A



  




  • a statement that management will uphold the safety requirements of the SCA & Regulations and resolve any issues regarding quality?

     

N/A



  




  • a statement that the quality system has the full support of the management who will ensure that adequate resources, including competent personnel, are provided to implement the program. State the title of the person responsible for the development and maintenance of the pressure piping construction program, with an explanation that this person has the defined authority and responsibility for implementation of the program and has direct access to, and support from, top management to resolve any implementation barriers?




     

Is there evidence that the management has provided adequate and competent resources for the construction activities?

Yes  ; No 

Does the person responsible for the program have direct access to the top manager?

Yes  ; No 





  

  • signature (with date) of an executive manager?

     

N/A



  




Reviewer’s Comments:

     




3.3.5

Management’s Responsibilities


Does this section:


  • include a statement and evidence that the management is committed to the development and implementation of a successful pressure piping construction program and that it will continually improve its effectiveness?




     


This question should be answered by the auditor upon completion of the audit.

     





  





  • establish that management will review the pressure piping construction program at appropriate intervals to ensure its continued suitability and effectiveness?

     


Is there evidence of owner/management conducting the review?

Yes  ; No 






  




  • include a statement that the management shall determine and provide adequate competent human resources and the necessary facilities and equipment to effectively implement the pressure piping construction activities?




     


Is there evidence of owner/management providing leadership, adequate infrastructure, competent resources, effective QMS, training?

Yes  ; No 





  




Reviewer’s Comments:

     



3.3.6

Contract Review

Are/is the:

  • responsibilities for contract review and agreement defined?




     

Review the contract document for the project and verify that the requirements are addressed.

Yes  ; No 





  

  • pressure piping construction requirements documented?

     

Yes  ; No 



  

  • scope of work defined?




     

Yes  ; No 



  

  • responsibilities for the supply of materials, construction drawings, design, design registration with ABSA, PWHT and pressure test defined in the contract?




     

Yes  ; No 



  




  • piping lot sizes for the purpose of NDE specified by the owner and agreed upon between the contracting parties before the start of the construction activities?




     

Yes  ; No 



  




  • requirement for a turnover package and contents thereof defined?




     

Yes  ; No 



  

  • responsibilities for certifying the construction using AB-83 or AB-83 Partial or AB-83F as the case may be defined?




     

Yes  ; No 



  

  • responsibilities for certifying the installation and readiness for operation using an AB-81 Form defined?




     

Yes  ; No 



  




Reviewer’s Comments:

     



3.3.7

Document & Data Control


  • Are the controls needed for the development, identification, storage, revision, protection, retrieval, retention time, and disposition of records addressed?

     

Are these controls being implemented?
Yes  ; No 




  

  • Has a document revision control process been developed and amendments to the documents are covered by an appropriate authorization, and processed in a manner which will ensure timely availability at the appropriate location?




     

Is a controlled copy of an up to date QMS manual available at the site?

Yes  ; No 





  

  • Is a current version of the quality manual provided and accepted by ABSA?




     

Yes  ; No 




  




  • Are all changes to documents managed appropriately including notification to the affected parties?




     

Yes  ; No 




  

  • Are the current issues of the appropriate documentation available at all relevant locations and to all relevant persons?




     

Yes  ; No 




  

  • Are superseded documents removed from use throughout the organization or are appropriately identified as superseded documents?




     

Yes  ; No 




  

  • Is the current revision status of documents identified?




     

Yes  ; No 




  




     

Yes  ; No 




  

  • Are documents of external origin identified and their distribution controlled?




     

Yes  ; No 




  




Reviewer’s Comments:

     



3.3.8

Piping Design

Scenario 1
If a pressure piping design is undertaken in-house by a manufacturer or by an owner who is also a manufacturer:

Check N/A  if scenario 1 does not apply to you.

  • Are design requirements such as the operating conditions, service requirements and other information needed to facilitate the safe design, construction, and inspection of the pressure piping system identified and documented?




     

Yes  ; No 




  

  • Are the personnel assigned to engineer the piping systems competent, and do they meet the qualification requirements of the company and of the applicable ASME B31 Code(s)?




     

Yes  ; No 




  

  • Are the design documents stamped by a P.Eng when a pressure piping system is required to be registered with ABSA?




     

Yes  ; No 




  




     

Yes  ; No 




  




     

Yes  ; No 




  

  • Are the design code edition and addenda of the applicable ASME construction codes, standards and other related documents available to design personnel and applied for pressure piping design?

     

Yes  ; No 




  




  • Do all design documents, including any revisions, have the required approval and are the revised documents made available at the point of use?




     

Yes  ; No 




  

  • Is an appropriate management of change process utilized to manage changes to the design?




     

Yes  ; No 




  

  • If the piping system’s internal volume exceeds 500 liters, are the design registration requirements with ABSA specified?




     

Yes  ; No 




  

  • Are the drawings reviewed and approved by engineering prior to release for construction?




     

Yes  ; No 




  

Scenario 2
If a pressure piping design is contracted out by an owner:

Check N/A  if scenario 2 does not apply to you.

  • Are competent in-house engineering resources assigned to prepare design basis memorandum (DBM) that identifies the design and operating conditions, the service requirements and other information needed to facilitate a safe design, construction and inspection of the pressure piping system. When no in-house engineering resources are available, is a process for contracting out the preparation of the DBM described?

     

Yes  ; No 




  

  • Is the DBM reviewed, approved and provided to the designer by the owner prior to the start of the design activity?




     

Yes  ; No 




  

  • Is the designer competent and meets the pressure piping design, code knowledge and qualification requirements of the owner, and of the applicable ASME B31 Code(s)?




     

Yes  ; No 




  




  • Are current ASME Codes available to the designer?




     

Yes  ; No 




  

  • Do the design documents prepared by the designer provide information about the code of construction including edition, proper material specifications, design pressure, maximum and minimum design temperatures, ASME B31.3 fluid category for process piping, type and extent of NDE required, hydro test pressure and medium, preheat and PWHT treatment requirements, joint design details, WPS and dimensions?




     

Yes  ; No 




  

  • Are the owner’s responsibilities assigned for the verification and acceptance of the design documents received back from the designer?




     

Yes  ; No 




  

  • If the piping system’s internal volume exceeds 500 liters, is responsibility for the registration of the design with ABSA assigned?




     

Yes  ; No 




  

  • Are the drawings reviewed and approved by the owner prior to release for construction?




     

Yes  ; No 




  

Scenario 3
If pressure piping design is supplied to the manufacturer by the owner:

Check N/A  if scenario 3 does not apply to you.


  • Do the construction drawings and/or other engineering documents received from the owner include information about the code of construction including edition, proper material specifications, design pressure, maximum and minimum design temperatures, ASME B31.3 fluid category for process piping, type and extent of NDE required, hydro test pressure and medium, preheat and PWHT treatment requirements, joint design details, WPS and dimensions, or, the information needed for construction of the piping is made available through appropriate documentation by the owner?

     

Yes  ; No 




  




  • When spool drawings or cut sheets are prepared by the manufacturer, are the drawings or cut sheets controlled and referenced by the owner-supplied construction or design drawings?




     

N/A  ; Yes  ; No 




  

  • Are the drawings reviewed and approved by the manufacturer prior to release for construction?




     

Yes  ; No 




  